  • One dead and two missing after CHOP parking garage under construction collapsed in Grays Ferry.
  • Roof segment fell, triggering progressive collapse across all seven levels.
  • The garage is owned by Children’s Hospital of Philadelphia and serves CHOP employees.

Garage Collapse

A seven-story parking garage under construction in Philadelphia collapsed, killing one and leaving two missing.

In doorbell video obtained by Action News, you can see the structure collapsing floor by floor

ABCABC

The collapse occurred when a precast concrete roof segment failed during installation.

Image from ABC
ABCABC

Three workers were rescued; one later died at the hospital.

The garage was being built for the Children's Hospital of Philadelphia.

Mayor Parker said all permits had been properly issued and inspections were up to date.

Fire Commissioner Thompson said the building is unstable and crews will have to deconstruct it.

Rescue Efforts

Emergency crews worked through the night to search for two missing workers.

Fire Commissioner Thompson said the plan was to deconstruct and delayer the building.

Image from Billy Penn at WHYY
Billy Penn at WHYYBilly Penn at WHYY

Ironworkers Local 401 confirmed some workers were union members.

Governor Shapiro tweeted prayers for those injured and missing.

Residents described hearing a loud boom and feeling their homes shake.

Investigation and Oversight

Installation of precast components falls under special inspections, not standard L&I review.

Valerie Moody of GAI was overseeing the inspections.

The general contractor was HSC Builders and Construction.

Investigators will analyze materials and construction procedures.

The project had been the subject of neighborhood protests.