UK committee voices concern over plan for multibillion-pound Sizewell nuclear plant

No framing issues found.

A British parliamentary committee has warned that the government plan to build an additional Sizewell nuclear plant would bring a "high level of risk" for the taxpayers over the rest of the century, local media reported Wednesday. The Parliamentary Public Accounts Committee said the cost of the Sizewell C nuclear reactor could spiral to almost £48 billion ($63.7 billion), The Guardian reported. This would leave bill payers on the hook to provide an extra £9.8 billion to construct the plant before 2040 and a further £12 billion over its 60-year operating life, they warned.

According to the committee, taxpayers and consumers face a "high level of risk," after the government agreed to take a near-45% stake in the nuclear plant, which is considered a successor project to the heavily delayed Hinkley Point C nuclear plant in Somerset. Last November, a review by the Nuclear Regulatory Taskforce, established by then-Prime Minister Keir Starmer, concluded that the UK has become the world’s most expensive country in which to build nuclear power plants, urging sweeping reforms to streamline regulation and reduce project costs.

Geoffrey Clifton-Brown, the committee chair, said: "The high level of risk borne by taxpayers and consumers for the construction of Sizewell C is extraordinary. Private investors look set for significant returns on their investments, while customers are likely to be saddled with higher energy bills." He urged the government to "focus on the successful delivery of this project." A government spokesperson said the report "completely ignores that investors are incentivized to complete construction as cheaply and quickly as possible" through the terms of the deal.

"Once operational, Sizewell C could save £2bn a year across the energy system, cutting costs for families up and down the country, and the project is already making good progress with over 2,000 workers on site," the spokesperson was quoted by the British daily as saying.

Read the original article on aa.com.tr (opens in a new tab)
About this analysis

Anadolu Agency reports the Public Accounts Committee's warning that Sizewell C could cost almost £48 billion and leave taxpayers and bill payers carrying a high level of risk, and it gives the government's reply. The figures match the Guardian's reporting, and every claim is attributed to the committee, its chair or a government spokesperson. Nothing in it misleads the reader.

What it gets right

  • “could spiral to almost £48 billion ($63.7 billion), The Guardian reported”

    The article gives the cost figure with its source and keeps it conditional with "could". The Guardian's own report uses the same figure in the same terms.

  • “an extra £9.8 billion to construct the plant before 2040 and a further £12 billion over its 60-year operating life, they warned”

    Each figure comes with its period and is attributed to the committee. It is not stated as the outlet's own fact.

  • “A government spokesperson said the report "completely ignores that investors are incentivized to complete construction as cheaply and quickly as possible"”

    The article puts the government's rebuttal next to the committee's warning and attributes it clearly. A reader sees both positions and knows who holds each.

Spot something we missed? Report this article

More from Anadolu Agency (English)

  1. 28 OctUK unveils energy support for 20M households, new aid for Ukraine0.0
  2. 28 OctUK premier, opposition leader clash over 'freedom of movement' ahead of Brussels summit0.0
  3. 26 OctBritish premier says revising UK’s Brexit deal with EU could ‘bring people together’0.0
  4. 26 OctBritain must be ready for war within 1,000 days: Defense secretary0.0
  5. 24 OctRestore Britain party leader questions support for Israel over reported Falklands stance0.0

Everything we scored from Anadolu Agency (English)