Contentious north-south electricity interconnector to run overground despite opposition

No framing issues found.

The long-awaited and controversial north-south electricity interconnector is to run overground despite trenchant local opposition, Minister of State for Energy Alan Dillon has confirmed. Twenty years after it was first proposed, and with continuing demand from local communities and politicians for the high-voltage power line to run underground , the long-delayed critical infrastructure project is now set to be completed and “energised” by 2031.

The Minister told TDs that State agency EirGrid “has determined that the project must be delivered as an overhead line. The Government has accepted the expert opinion.” Speaking in the Dáil during questions on climate, energy and the environment, the Minister said: “It is progressing. It is going to happen.” Acknowledging local opposition to overground pylons that will run from Co Meath to Co Tyrone, he said “the notion of undergrounding the project has been comprehensively assessed on several occasions dating back to 2008”.

Successive independent reports found an overhead line “is the most appropriate means of delivery”. He said in March 2023 the government published an independent report on the project “that concluded it was not feasible to run the north-south interconnector underground”. And he insisted “public support is key in enabling delivery of the project” and it plays a “crucial role in EirGrid’s plan”. However, Fine Gael TD for Cavan-Monaghan David Maxwell said there needed to be “meaningful and proper consultation between EirGrid and the communities affected” because they have “serious objections” and “need to have their concerns taken seriously and be given clear answers”.

He said campaign groups in Armagh and Tyrone “continue legal challenges” and raised concerns over the visual impact and pylon placement. Maxwell asked: “ould we have the Northern section underground and the Southern section overground?” [ EirGrid to pay landowners up to €50,000 per pylon along its north-south powerline Opens in new window ] Sinn Féin energy spokesman Darren O’Rourke said there was “massive local opposition” and insisted the 2023 report “does not say it is not viable to go underground and it is very critical of EirGrid and how it has conducted its analysis over the years”.

“Until we get that issue addressed there is no community support for this. If an adequate review is done it will show undergrounding is viable and this project can be delivered.” He warned “this project will not be delivered by forcing it through, such is the level of local opposition”. An independent assessment would point to undergrounding because “otherwise we are on the road to nowhere”. The Minister said reports had shown undergrounding would be up to three times more expensive than the overhead option, which is “the most appropriate option from a technical perspective”.

He added: “The planning conditions are commencing and construction is commencing. It is critical it be delivered and benefit all of Ireland in regard to our electrification process.”

Read the original article on irishtimes.com (opens in a new tab)
About this analysis

The Irish Times reports the Minister of State for Energy's confirmation that the north-south interconnector will run overground, and sets his case against the objections of a Fine Gael TD and the Sinn Féin energy spokesman. Every contested claim, including the cost comparison and the reading of the 2023 report, is attributed to the person making it. Nothing in the article misleads its reader.

What it gets right

  • “insisted the 2023 report “does not say it is not viable to go underground and it is very critical of EirGrid and how it has conducted its analysis over the years””

    The article puts a direct challenge to the Minister's reading of the 2023 report on the record. The government's account does not stand alone.

  • “The Minister said reports had shown undergrounding would be up to three times more expensive than the overhead option”

    The cost figure is attributed to the Minister and the reports he cites. It is not stated as fact in the outlet's own voice.

  • “campaign groups in Armagh and Tyrone “continue legal challenges””

    The article tells the reader that organised opposition and live legal action continue. It does not present the project as settled.

Spot something we missed? Report this article

More from The Irish Times

  1. 5 NovChildren can be taught about climate change without alarm or guilt 0.0
  2. 4 NovRoebuck Foods seeks €10m as it eyes up climate companies Glasport and Rumen Tech0.0
  3. 4 NovHydrogen could power Ireland’s expanding data centre sector, Cork conference to hear3.0
  4. 4 NovClimate council criticises failure to invest in nature to protect against extreme weather 0.0
  5. 3 NovIreland records sixth consecutive warmer-than-average October, Met Éireann says0.0

Everything we scored from The Irish Times